On November 26, 2019, at the office of Doosan Heavy Industries Vietnam (Hanoi), Construction Corporation No. 1 (CC1) was honored to be awarded by Doosan General Contractor as the best Construction contractor for the project. Vinh Tan 4 thermal power plant cluster project (600MW x 3 Units) in the period from July 2015 to November 2017. This award is based on the assessment and recognition of the labor achievements that CC1 has contributed, making an important contribution to the success of the project.
Mr. Nguyen Duc Dung – Deputy General Director of CC1 received the best construction contractor award
Vinh Tan 4 Thermal Power Plant is an urgent project, included in the National Power Development Plan for the period 2011-2020 with a vision to 2030 (General Power Planning 7) of the Government, built in Hanoi. Vinh Tan Power Center, Vinh Tan Commune, Tuy Phong District, Binh Thuan Province
The project was started in March 2014 and inaugurated the entire factory on September 21, 2019. Important progress milestones of the project have all been reached and exceeded earlier than planned: Unit S2 and shared items were handed over and put into commercial operation from December 6, 2017, 20 earlier than planned. date and level of PAC. Unit S1 and the entire plant have been handed over and put into commercial operation since March 31, 2018 and especially unit 3 of the expanded plant has completed power generation nearly 3 months earlier than planned. This project has an important meaning for ensuring electricity supply of the whole country, especially for the southern region. Vinh Tan 4 Thermal Power Plant Project has been selected by the Ministry of Construction to attach a project sign to celebrate the 60th anniversary of the construction industry's traditional day. Along with Lai Chau hydroelectricity, Vinh Tan 4 Thermal Power Project is honored to be one of the two projects of the Power sector selected to be mounted by the Ministry of Construction because it has successfully completed the criteria of progress, quality and efficiency. fruit.
Vinh Tan 4 Thermal Power Plant Project (600MW x 3 Units)
During the process of construction, installation and testing of the project until it is put into operation, the units are guaranteed to promote their designed capacity, meeting the requirements for power generation for the national power system. Up to now, the plant has generated electricity output of over 10.8 billion kWh on the national grid; At the same time, it also ensures the good implementation of regulations on environmental protection.
The CC1 leadership representative received the award presented by Mr. Chahn Gyu Kim - Project Manager of Doosan Heavy Industries Vietnam.
To achieve these achievements, CC1's leaders and employees have worked hard, trying to design scientific construction methods to save time, human resources and costs, bringing the items that CC1 is in charge of finishing 3 months ahead of schedule. The award has contributed to affirming the construction capacity and management capacity of CC1 staff.
Along with Vinh Tan 4 Thermal Power Plant, CC1 has also completed many key thermal power projects in recent years such as: Mong Duong 2 Thermal Power Plant, Nghi Son 1 Thermal Power Plant, 2 Thermal Power Plant, Duyen Hai 3 Thermal Power Plant Extension, Thermal Power Plant O Mon, Van Phong…
One of the construction items within the scope of CC1