Quang Trach 1 thermal power plant project is invested by EVN. This is a project with a capacity of 1,200 MW, located in the Quang Trach Power Center (2,400 MW) in Vinh Son village, Quang Dong commune, Quang Trach district, Quang Binh province.


According to Vietnam Energy Magazine The consortium of Mitsubishi Corporation (Japan), Hyundai Engineering and Construction (Korea), Construction Corporation No. 1 (Consortium MC – HDEC – CC1) has just been approved by Electricity of Vietnam (EVN) to win the bidding package. No. 15 (EPC-QT1) Design, supply of goods and construction (EPC) of Quang Trach 1 thermal power plant project.

At the time of bid closing, two bidders submitted their bids. The MC - HDEC - CC1 consortium won the bid for more than VND 30,236 billion, down VND 4.1 billion compared to the package price. The Daewoo E&C – LILAMA consortium was eliminated in the evaluation of technical proposals.

Quang Trach 1 thermal power plant project is invested by EVN. This is a project with a capacity of 1,200 MW, located in the Quang Trach Power Center (2,400 MW) in Vinh Son village, Quang Dong commune, Quang Trach district, Quang Binh province. (Read more..)